文(wen)章(zhang)來源:內蒙古國資委 發布時間:2021-04-29
隨著(zhu)內(nei)蒙古東部地(di)區進入公路(lu)施工(gong)(gong)(gong)的(de)有(you)利(li)季節,由內(nei)蒙古高路(lu)公司和赤(chi)峰市人民政(zheng)府合作的(de)PPP項目--丹(dan)錫高速公路(lu)克(ke)(ke)什(shen)克(ke)(ke)騰至承德聯(lian)絡線(xian)克(ke)(ke)什(shen)克(ke)(ke)騰(經棚)至烏(wu)蘭布統(tong)(蒙冀(ji)界(jie))段高速公路(lu),在做好疫情防控工(gong)(gong)(gong)作的(de)基礎上,于4月15日召(zhao)開(kai)復(fu)(fu)工(gong)(gong)(gong)動員會,吹響2020年全線(xian)復(fu)(fu)工(gong)(gong)(gong)的(de)號(hao)角。目前全線(xian)2359名筑路(lu)人和400余(yu)套(tao)施工(gong)(gong)(gong)機械(xie)已(yi)投入生產一線(xian),進入緊張有(you)序的(de)建設施工(gong)(gong)(gong)中(zhong)。
此(ci)前(qian)(qian),經烏高速公路管(guan)理公司為(wei)充分(fen)做足復(fu)工準備,不(bu)斷(duan)優化(hua)方案、強(qiang)化(hua)預(yu)案,分(fen)別召(zhao)開項(xiang)目(mu)(mu)防(fang)控(kong)工作研究部(bu)署(shu)會和復(fu)工前(qian)(qian)工作部(bu)署(shu)會,分(fen)析(xi)研判存(cun)在和面臨有(you)關(guan)問題(ti)的(de)同(tong)時,深(shen)入開展(zhan)復(fu)工準備專項(xiang)檢查,督促指導各參建單位(wei)在抓緊抓實(shi)抓細本(ben)單位(wei)疫情(qing)防(fang)控(kong)的(de)基礎上,進一步明(ming)確目(mu)(mu)標、超前(qian)(qian)謀劃、科(ke)學組織(zhi),為(wei)項(xiang)目(mu)(mu)平安穩妥(tuo)復(fu)工打下了堅實(shi)基礎。
該項目全(quan)(quan)長96.151公里,總投(tou)資(zi)60.63億(yi)元,建(jian)設工期4年,全(quan)(quan)線2019年9月正式開工,已累計完成(cheng)投(tou)資(zi)25.5億(yi)元,2020計劃完成(cheng)剩余(yu)路(lu)基(ji)土石(shi)方、大中(zhong)橋(qiao)、涵洞、路(lu)面底基(ji)層施工,計劃完成(cheng)投(tou)資(zi)12億(yi)元。
【責任編輯:語謙】