文章來源:中國華能(neng)集團有限公(gong)司(si) 發布時間:2019-06-14
6月9日0時(shi)0分,華能(neng)瀾滄(cang)江公司大華橋水電站首臺機組通(tong)過72小時(shi)試運(yun)行,正式投入商業運(yun)行。
大華橋(qiao)水電(dian)站是瀾滄江(jiang)上游曲(qu)孜卡至苗尾河段水電(dian)梯級開發(fa)方案里(li)規劃建設的第七級電(dian)站。電(dian)站總裝機(ji)容量(liang)92萬千(qian)(qian)(qian)瓦(wa)(wa),將安(an)裝4臺23萬千(qian)(qian)(qian)瓦(wa)(wa)混流式水輪(lun)發(fa)電(dian)機(ji)組,多年平均年發(fa)電(dian)量(liang)達39.18億(yi)千(qian)(qian)(qian)瓦(wa)(wa)時。
在電(dian)站建(jian)設過(guo)程(cheng)(cheng)中,瀾滄(cang)江公司大力實施科(ke)技(ji)(ji)創新和管理創新,累計獲得國(guo)家(jia)專利15項(xiang)(xiang)(xiang),省部級科(ke)技(ji)(ji)進步(bu)獎(jiang)10項(xiang)(xiang)(xiang)、設計獎(jiang)3項(xiang)(xiang)(xiang)、QC成果獎(jiang)12項(xiang)(xiang)(xiang)、施工(gong)(gong)工(gong)(gong)法8項(xiang)(xiang)(xiang)、管理創新成果獎(jiang)2項(xiang)(xiang)(xiang)。電(dian)站首(shou)次在國(guo)內(nei)大江大河中成功應用(yong)膠凝砂礫石(shi)(CSG)過(guo)水(shui)圍堰;探索(suo)“互聯(lian)網(wang)+水(shui)電(dian)工(gong)(gong)程(cheng)(cheng)”,全面推行(xing)可視(shi)化施工(gong)(gong)法,并采用(yong)數字大壩技(ji)(ji)術全程(cheng)(cheng)監(jian)控施工(gong)(gong);大壩混凝土澆(jiao)筑(zhu)打破(po)了國(guo)內(nei)同(tong)類(lei)大壩壩體最(zui)小滲(shen)漏量(liang)紀錄;機(ji)電(dian)安裝質量(liang)優(you)良,機(ji)組運行(xing)振(zhen)動擺度(du)創國(guo)內(nei)同(tong)類(lei)型機(ji)組最(zui)優(you);建(jian)成魚(yu)類(lei)增(zeng)殖站,在國(guo)內(nei)外首(shou)次人工(gong)(gong)繁殖成功灰裂(lie)腹(fu)魚(yu)、瀾滄(cang)裂(lie)腹(fu)魚(yu);建(jian)成自動化、智能(neng)化升魚(yu)機(ji)工(gong)(gong)程(cheng)(cheng),升魚(yu)高度(du)居世界第(di)二。
瀾滄江公司(si)深入踐(jian)行“建設一座電站(zhan),帶動一方(fang)經濟,保(bao)護一片環境(jing),造福一方(fang)百姓,共(gong)建一方(fang)和(he)諧”社會(hui)責任理念,通過電站(zhan)建設、“新百千萬(wan)工程”,有力帶動了當地經濟社會(hui)發展。
【責任編輯:駱秧秧】