文章來源:中(zhong)國能源建(jian)設(she)集團有限公(gong)司 發布(bu)時(shi)間:2019-03-07
近日,由中國(guo)能建中電(dian)工程華東院承擔常規島(dao)設計的“華龍一號”全球首堆示范工程福清核電(dian)5、6號機組(zu)220千伏倒送電(dian)圓滿完成,為機組(zu)后(hou)續安裝、調試等工作創(chuang)造了有利條件。
華(hua)東院秉(bing)承“精心設(she)計(ji)、優(you)質服務(wu)”的理(li)念(nian),承擔了與(yu)220千(qian)(qian)(qian)伏倒送電(dian)相關(guan)的220千(qian)(qian)(qian)伏開(kai)關(guan)站(zhan)(TD)、輔助變壓器區域及公用6.6千(qian)(qian)(qian)伏配(pei)電(dian)間(jian)(JX)、220千(qian)(qian)(qian)伏繼電(dian)器室(TC)內的系統以及相關(guan)的土建(jian)(jian)、建(jian)(jian)筑、暖(nuan)通、消(xiao)防、繼電(dian)保(bao)護、遠動(dong)和通信等設(she)計(ji)內容。
本次220千伏倒(dao)送(song)(song)電(dian)工(gong)程建安工(gong)作共歷時(shi)14個月。早在2016年(nian)(nian)10月,華東(dong)院福清(qing)核電(dian)5、6號機組(zu)工(gong)程組(zu)為(wei)(wei)保證本次倒(dao)送(song)(song)電(dian)順利(li)通過(guo),制定了詳細的(de)(de)220千伏倒(dao)送(song)(song)電(dian)相關圖(tu)(tu)紙出(chu)(chu)版計劃,最終(zhong)所有圖(tu)(tu)紙均按(an)時(shi)或(huo)提前出(chu)(chu)版,為(wei)(wei)此次220千伏倒(dao)送(song)(song)電(dian)的(de)(de)一(yi)次成功打下了良好的(de)(de)基礎。2018年(nian)(nian)春節前后(hou),工(gong)程組(zu)電(dian)氣主設和現場(chang)工(gong)代加班加點處理(li)現場(chang)提出(chu)(chu)的(de)(de)相關技(ji)術問題,為(wei)(wei)確保220千伏倒(dao)送(song)(song)電(dian)的(de)(de)按(an)時(shi)完(wan)成貢獻了重要的(de)(de)力量。
此次倒送電(dian)成(cheng)功后,220千伏輔助電(dian)源即為(wei)可用,為(wei)后續的除鹽水(shui)(shui)生產廠房制水(shui)(shui)、主控室(shi)可用、泵房進水(shui)(shui)、主泵組裝及試車等(deng)諸多工程(cheng)節點提供(gong)了(le)電(dian)源保(bao)證,為(wei)“華龍(long)一號(hao)”全球首堆示范工程(cheng)的順利建(jian)設奠定了(le)堅實基礎(chu)。
【責任編(bian)輯:駱(luo)秧秧】