文章來源(yuan):中國南方電網有限責任公司 發布時間:2010-07-07
在多方共同努力之下,6月15日,受阻長達5年的廣東肇慶110千伏水邊變電站輸變電工程順利投運,工程的投運將極大地改善高要市金渡鎮、蜆崗鎮的投資環境,滿足新上項目對電力的需求。
該工(gong)(gong)(gong)程(cheng)(cheng)自(zi)2003年經(jing)批準立項(xiang)建設以(yi)來,多次遭到高要(yao)市金(jin)渡(du)鎮水邊村(cun)(cun)一些村(cun)(cun)民阻撓施工(gong)(gong)(gong),使(shi)工(gong)(gong)(gong)程(cheng)(cheng)建設進展(zhan)緩慢。肇慶供電(dian)局專(zhuan)門成立青賠工(gong)(gong)(gong)作(zuo)小(xiao)組,想方設法與(yu)鎮街聯(lian)動(dong),分(fen)片區逐級(ji)落(luo)實責(ze)任,耐心(xin)做好(hao)解釋說服工(gong)(gong)(gong)作(zuo),及時解決青賠、拆遷等問(wen)題(ti)。經(jing)過(guo)全(quan)體施工(gong)(gong)(gong)人(ren)員的艱苦奮(fen)戰,該輸電(dian)線(xian)路工(gong)(gong)(gong)程(cheng)(cheng)自(zi)4月10日(ri)開(kai)工(gong)(gong)(gong)后(hou),于6月4日(ri)全(quan)部完成,并于6月12日(ri)通過(guo)驗(yan)收。