免费菠萝视频app下载  >  新聞發布  >  央企聯播 > 正文
華電集團靈武二期百萬空冷機組三號鍋爐鋼架提前吊裝

文章來(lai)源:中國華電集團公司(si)  發布(bu)時間:2010-05-20

  5月16日上午9時16分,中國華電集團公司寧夏靈武發電有限公司二期兩臺100萬千瓦空冷機組工程三號鍋爐鋼架在鞭炮聲中緩緩起吊,安裝就位,較里程碑計劃提前82天,為機組早日投產和創“國優金獎”工程奠定了基礎。

  該(gai)公司二期(qi)工(gong)(gong)(gong)程(cheng)(cheng)是世(shi)界首臺百萬(wan)千瓦空冷機(ji)組(zu),也是寧東(dong)能(neng)源(yuan)化工(gong)(gong)(gong)基地(di)“一號(hao)工(gong)(gong)(gong)程(cheng)(cheng)”。自2008年12月(yue)27日(ri)“破土(tu)”動工(gong)(gong)(gong)以來,該(gai)公司克服時間緊、任(ren)務(wu)重、環(huan)境條件差(cha)、無施工(gong)(gong)(gong)經驗(yan)(yan)可借(jie)鑒等諸多困難,充分發揮業主(zhu)單位在工(gong)(gong)(gong)程(cheng)(cheng)管理中的(de)主(zhu)導(dao)作用,組(zu)織(zhi)參建(jian)各(ge)(ge)方超前謀劃(hua),精心(xin)組(zu)織(zhi),認真準備(bei)(bei)并落實(shi)(shi)各(ge)(ge)項(xiang)施工(gong)(gong)(gong)措施方案,始(shi)(shi)終(zhong)以“創國優金獎”為(wei)(wei)目(mu)標,高起點、高標準,嚴(yan)格現場(chang)施工(gong)(gong)(gong)管理和階段驗(yan)(yan)收,規范各(ge)(ge)項(xiang)工(gong)(gong)(gong)程(cheng)(cheng)管理程(cheng)(cheng)序(xu),施工(gong)(gong)(gong)安全、質(zhi)量(liang)(liang)、工(gong)(gong)(gong)期(qi)、造(zao)(zao)價始(shi)(shi)終(zhong)處于受控(kong)狀態。自3月(yue)16日(ri)三(san)號(hao)主(zhu)廠房和鍋(guo)爐(lu)房順利實(shi)(shi)現澆(jiao)筑第一方混(hun)(hun)凝土(tu),至5月(yue)16日(ri)實(shi)(shi)現三(san)號(hao)鍋(guo)爐(lu)鋼(gang)(gang)架的(de)吊(diao)裝,土(tu)建(jian)專(zhuan)業在確保澆(jiao)注混(hun)(hun)凝土(tu)質(zhi)量(liang)(liang)的(de)同時,精心(xin)組(zu)織(zhi),加班加點,合理調(diao)配施工(gong)(gong)(gong)機(ji)械、施工(gong)(gong)(gong)人員(yuan),在短短2個月(yue)的(de)時間里,完(wan)成了鍋(guo)爐(lu)基礎13000多方混(hun)(hun)凝土(tu)的(de)澆(jiao)筑任(ren)務(wu),為(wei)(wei)鋼(gang)(gang)架的(de)吊(diao)裝爭得了時間,創造(zao)(zao)了條件。與(yu)此同時,加大圖(tu)紙和鋼(gang)(gang)架設備(bei)(bei)的(de)催交(jiao)力度(du),嚴(yan)把質(zhi)量(liang)(liang)驗(yan)(yan)收關,從源(yuan)頭上控(kong)制和杜(du)絕了鍋(guo)爐(lu)鋼(gang)(gang)架帶缺陷吊(diao)裝。

掃一掃在手機打開當前頁

打印

 

關閉窗口

lutube-lutube下载-lutube下载地址-lutube最新地址 lutube-lutube下载-lutube下载地址-lutube最新地址 lutube-lutube下载-lutube下载地址-lutube最新地址