文章來源:中國冶(ye)金(jin)科工集團(tuan)公(gong)司(si) 發布時間:2009-12-26
截至12月20日,中冶二冶承建的烏海吉蘭泰電石爐2號爐調試工作全部結束,具備投產條件。
烏海吉蘭泰電(dian)(dian)石爐工(gong)程(cheng)2號爐主要電(dian)(dian)氣設(she)備(bei)高壓(ya)系統有(you)3臺9000千(qian)伏安(an)變壓(ya)器、35千(qian)伏高壓(ya)柜(ju)8面(mian)、10千(qian)伏高壓(ya)柜(ju)6面(mian)。低壓(ya)系統有(you)循(xun)環水、低壓(ya)柜(ju)若干(gan)。電(dian)(dian)調(diao)(diao)(diao)(diao)(diao)隊負(fu)責電(dian)(dian)氣設(she)備(bei)調(diao)(diao)(diao)(diao)(diao)整試(shi)(shi)(shi)驗和(he)高、低壓(ya)送配電(dian)(dian)、計(ji)算機(ji)控制(zhi)及輸(shu)入輸(shu)出(chu)點校核等任務。自(zi)8月底(di)進入調(diao)(diao)(diao)(diao)(diao)試(shi)(shi)(shi)階段以來,由(you)于(yu)(yu)設(she)計(ji)方面(mian)存(cun)(cun)在(zai)誤差(cha),大部分(fen)設(she)計(ji)存(cun)(cun)在(zai)漏洞,給調(diao)(diao)(diao)(diao)(diao)試(shi)(shi)(shi)工(gong)作帶來極大困(kun)難,調(diao)(diao)(diao)(diao)(diao)試(shi)(shi)(shi)人員(yuan)在(zai)復雜(za)而沒(mei)有(you)頭緒的(de)施工(gong)現場,面(mian)對著漏洞百出(chu)的(de)設(she)計(ji),白天在(zai)施工(gong)現場邊(bian)調(diao)(diao)(diao)(diao)(diao)試(shi)(shi)(shi)邊(bian)熟悉工(gong)藝流(liu)程(cheng),與設(she)備(bei)單(dan)位(wei)進行(xing)改正(zheng)(zheng)設(she)計(ji)中存(cun)(cun)在(zai)的(de)問(wen)題,晚(wan)上依據原理(li)(li)和(he)設(she)備(bei)說明書及國標重新(xin)改正(zheng)(zheng)原理(li)(li)圖,制(zhi)定切實可行(xing)的(de)施工(gong)方案,使1號電(dian)(dian)石爐于(yu)(yu)11月底(di)順利投產。在(zai)調(diao)(diao)(diao)(diao)(diao)試(shi)(shi)(shi)2號爐10千(qian)伏高壓(ya)柜(ju)時(shi),由(you)于(yu)(yu)存(cun)(cun)在(zai)10千(qian)伏中壓(ya)補償,在(zai)以前的(de)施工(gong)中從圍見過(guo),技術(shu)人員(yuan)認真分(fen)析(xi)原理(li)(li),虛(xu)心請教,一步步進行(xing)調(diao)(diao)(diao)(diao)(diao)試(shi)(shi)(shi),經過(guo)努力,最(zui)終(zhong)在(zai)單(dan)體試(shi)(shi)(shi)車成功的(de)基(ji)礎上,順利具備(bei)投產條件(jian)。