文(wen)章來源(yuan):中(zhong)國華能集團公司 發布時間:2009-08-14
華能巢湖發電有限責任公司一號60萬千瓦機組于2008年8月9日20點55分順利通過168小時試運,比計劃工期提前4個月投產發電。
巢湖一期工(gong)(gong)(gong)(gong)程(cheng)裝備2臺(tai)國(guo)產60萬千瓦機組,經(jing)過(guo)全面優化(hua)設計,工(gong)(gong)(gong)(gong)程(cheng)顯現出(chu)(chu)造價(jia)(jia)低、占(zhan)地省的突出(chu)(chu)優勢。工(gong)(gong)(gong)(gong)程(cheng)計劃靜態投資為36.34億元(yuan),與可研相比節約造價(jia)(jia)約8億元(yuan),千瓦造價(jia)(jia)僅為3000元(yuan)左右(you),為國(guo)產60萬千瓦新建(jian)工(gong)(gong)(gong)(gong)程(cheng)造價(jia)(jia)最低水平。廠區平面布置(zhi)緊(jin)湊,主廠區占(zhan)地僅23公頃,比工(gong)(gong)(gong)(gong)程(cheng)可研階段設計用地節約40%,與國(guo)內(nei)同類型新建(jian)同容量等級電廠相比占(zhan)地最少。