文章來源:中國葛洲壩集團公(gong)司 發(fa)布時間:2008-12-26
12月25日,隨著金(jin)安橋水(shui)電站(zhan)廠房4號機下游墻牛腿層最后一倉(cang)混凝土順利開倉(cang)澆筑,金(jin)安橋項目部2007年度廠房施工重大(da)節(jie)點目標(biao)順利實現。中國(guo)葛洲壩集團(tuan)股份有限(xian)公司承建的金(jin)安橋水(shui)電站(zhan)廠房工程即將(jiang)迎來全(quan)面竣(jun)工。
金安橋水電站廠房于2006年12月(yue)開工(gong)(gong)(gong)(gong),因施(shi)工(gong)(gong)(gong)(gong)面交(jiao)面日期比合同工(gong)(gong)(gong)(gong)期滯后(hou)達3個多月(yue),施(shi)工(gong)(gong)(gong)(gong)時間非常緊張。承擔施(shi)工(gong)(gong)(gong)(gong)任務的葛洲壩西南(nan)施(shi)工(gong)(gong)(gong)(gong)局金安橋項目部牢固樹立(li)“又好又快(kuai)(kuai)、好中求快(kuai)(kuai)”的指導思想, 精心籌劃,周(zhou)密布(bu)置,優化施(shi)工(gong)(gong)(gong)(gong)資源配置,不(bu)斷加(jia)快(kuai)(kuai)施(shi)工(gong)(gong)(gong)(gong)進度(du)(du),11、12月(yue)份混凝土澆筑(zhu)方量不(bu)斷創(chuang)新(xin)紀錄。在加(jia)快(kuai)(kuai)施(shi)工(gong)(gong)(gong)(gong)進度(du)(du)的同時,項目部結合廠房段混凝土施(shi)工(gong)(gong)(gong)(gong)的特點和難(nan)點,嚴格執行三級檢驗制度(du)(du),加(jia)強過(guo)程控制,有(you)效(xiao)改(gai)進施(shi)工(gong)(gong)(gong)(gong)工(gong)(gong)(gong)(gong)藝,繼(ji)10月(yue)份首創(chuang)廠房標段“樣板倉”后(hou),12月(yue)份又連(lian)創(chuang)三個“樣板倉”,為(wei)工(gong)(gong)(gong)(gong)程質量的進一(yi)步提升(sheng)創(chuang)造了條件。
在(zai)成功達到(dao)節點工(gong)期的慶祝儀式上(shang),葛洲壩(ba)西南工(gong)程(cheng)(cheng)局領導要求金安橋(qiao)項(xiang)目部認真規劃2008年的各項(xiang)工(gong)作,團(tuan)結(jie)一致,拼(pin)搏創新,把金安橋(qiao)水(shui)電站廠房工(gong)程(cheng)(cheng)打(da)造成“精品工(gong)程(cheng)(cheng)”、“樣板工(gong)程(cheng)(cheng)”、“業(ye)主滿意工(gong)程(cheng)(cheng)”,展示葛洲壩(ba)“文明之(zhi)師、威武之(zhi)師”的良(liang)好(hao)精神(shen)風貌。
業主華(hua)睿集團副總裁、金(jin)安(an)橋公司總經理(li)劉(liu)興榮高(gao)興地說,葛(ge)洲(zhou)壩(ba)不愧是一支特(te)別(bie)(bie)能打硬仗(zhang)、特(te)別(bie)(bie)能戰斗的隊(dui)伍,選擇葛(ge)洲(zhou)壩(ba)就是選擇了成(cheng)功。他表示,要對金(jin)安(an)橋項目部給(gei)予獎勵。
金安橋水電站工程是金沙江中游河段規劃的第五級電站。電站裝機4臺,單機容量60萬千瓦,計劃首臺機組發電時間為2009年12月。2006年4月8日,中國葛洲壩集團股份有限公司中標金安橋水電站廠區土建、機電及金結安裝工程。