文章來源(yuan):國家電網公司 發布時間:2014-01-07
2012年12月29日下午,為門頭溝石門營地區保障性住房提供電源的石門營新八區配電室完成最后的送電工作,標志著北京市2012年保障性住房配套電力設施建設工程全面完工。
據了解,2012年北(bei)京市保障(zhang)性住房竣工(gong)(gong)(gong)計(ji)劃共計(ji)80項,已全部按時(shi)送(song)電(dian)。全年送(song)電(dian)戶(hu)數9萬戶(hu),送(song)電(dian)容量22萬千(qian)伏安(an),新建(jian)21座(zuo)開閉站、264座(zuo)配電(dian)室(shi),工(gong)(gong)(gong)程(cheng)量比2011年增長10%。北(bei)京市電(dian)力公司將(jiang)保障(zhang)房用電(dian)報裝項目列入重(zhong)點工(gong)(gong)(gong)程(cheng),開辟綠(lv)色通道,采取倒排工(gong)(gong)(gong)期的(de)形式,保證工(gong)(gong)(gong)程(cheng)實施(shi)(shi)進(jin)度(du)(du)。在對各(ge)(ge)項工(gong)(gong)(gong)作提出時(shi)限要(yao)求(qiu)的(de)基礎上(shang),壓縮各(ge)(ge)業(ye)(ye)務(wu)環(huan)節(jie)工(gong)(gong)(gong)作時(shi)限,統籌協調各(ge)(ge)相關業(ye)(ye)務(wu)環(huan)節(jie)的(de)實施(shi)(shi)。建(jian)立(li)定點聯系(xi)制(zhi)度(du)(du),主動(dong)走訪項目建(jian)設單位(wei),跟蹤掌握工(gong)(gong)(gong)程(cheng)進(jin)度(du)(du)等(deng)情(qing)況,及時(shi)協調處理(li)施(shi)(shi)工(gong)(gong)(gong)過程(cheng)中存在的(de)問題(ti),確保質量和進(jin)度(du)(du)。