文(wen)章來源:中國華電集團(tuan)公司 發(fa)布時間:2012-03-23
3月17日,華電寧(ning)夏靈武發電有限公司二期(qi)工程#4機組(zu)鍋爐點火(huo)一次成功(gong),此次點火(huo)成功(gong)為即將進(jin)行的(de)鍋爐吹管(guan)工作(zuo)打(da)下了牢(lao)固的(de)基(ji)礎。
#4機組進(jin)(jin)入安裝(zhuang)調(diao)試(shi)高(gao)(gao)峰期(qi)以來(lai),靈武公(gong)司(si)將“創先(xian)爭優”融(rong)入工(gong)(gong)程(cheng)建(jian)(jian)設(she)(she),開(kai)展(zhan)(zhan)了(le)“大(da)干(gan)60天,投(tou)產#4機,為(wei)建(jian)(jian)黨90周(zhou)年獻(xian)禮”活(huo)(huo)動,激(ji)發廣大(da)黨員(yuan)(yuan)職工(gong)(gong)活(huo)(huo)力,團結各(ge)參建(jian)(jian)單(dan)位克(ke)服重重困(kun)難(nan)(nan)確保(bao)機組早日高(gao)(gao)效投(tou)產。在進(jin)(jin)度(du)(du)管理方(fang)面(mian),該公(gong)司(si)超前(qian)做(zuo)好(hao)各(ge)項(xiang)施(shi)(shi)(shi)工(gong)(gong)準(zhun)備(bei)(bei)工(gong)(gong)作,進(jin)(jin)一步細(xi)化#4機組鍋爐點火前(qian)施(shi)(shi)(shi)工(gong)(gong)、調(diao)試(shi)計劃,將計劃完成(cheng)時(shi)(shi)間精確到小時(shi)(shi)。同時(shi)(shi),嚴格(ge)控制計劃完成(cheng)情況(kuang),不(bu)斷(duan)加大(da)設(she)(she)備(bei)(bei)催交力度(du)(du),保(bao)證(zheng)了(le)現場的連(lian)續施(shi)(shi)(shi)工(gong)(gong)。為(wei)正確處理施(shi)(shi)(shi)工(gong)(gong)主線(xian)與輔(fu)線(xian)的關系,在確保(bao)主線(xian)工(gong)(gong)程(cheng)工(gong)(gong)期(qi)目標的同時(shi)(shi),扎(zha)實推(tui)進(jin)(jin)輔(fu)線(xian)工(gong)(gong)作的順(shun)利(li)開(kai)展(zhan)(zhan),并充分(fen)協調(diao)參建(jian)(jian)各(ge)方(fang)人員(yuan)(yuan),克(ke)服了(le)施(shi)(shi)(shi)工(gong)(gong)場地緊張、寒冷季節施(shi)(shi)(shi)工(gong)(gong)難(nan)(nan)、施(shi)(shi)(shi)工(gong)(gong)人員(yuan)(yuan)少等(deng)困(kun)難(nan)(nan),為(wei)#4爐一次點火成(cheng)功里程(cheng)碑(bei)節點的提前(qian)高(gao)(gao)質量完成(cheng)提供(gong)了(le)保(bao)證(zheng)。
下一步,靈武公司將繼續深化工(gong)(gong)程管理創新,精心(xin)施工(gong)(gong)、精心(xin)調試,確保#4機(ji)組(zu)投產各項指標水平優于#3機(ji)組(zu)。