文章來(lai)源:中國鐵路工程總(zong)公司 發布時間:2010-10-10
9月26日(ri),中國鐵(tie)路工(gong)(gong)程總(zong)公司所屬中鐵(tie)九局承(cheng)建的(de)(de)靖宇至松(song)(song)江河鐵(tie)路工(gong)(gong)程下山頭隧(sui)道斜(xie)(xie)井正(zheng)式開工(gong)(gong)。下山頭隧(sui)道全長7960米,是(shi)宇松(song)(song)線(xian)施工(gong)(gong)難度最大、工(gong)(gong)期最緊的(de)(de)重點控制性(xing)工(gong)(gong)程。為(wei)了確保下山頭隧(sui)道早日(ri)貫通,項目經理(li)部在DK58+500設置了斜(xie)(xie)井,斜(xie)(xie)井長893米,承(cheng)擔正(zheng)洞3500米的(de)(de)施工(gong)(gong)任務。