文章來源(yuan):中國葛洲(zhou)壩集團公司 發布(bu)時間(jian):2010-07-16
7月(yue)初(chu),由葛洲(zhou)壩集團西南分公司景洪項目部(bu)承建的景洪水電站C1標2號表孔尾坎(kan)澆筑完(wan)成(cheng),標志著主(zhu)體工(gong)程(cheng)C1標右岸(an)土建及金屬結構安裝工(gong)程(cheng)全線完(wan)工(gong)。
由(you)葛(ge)洲(zhou)壩集(ji)團承擔施工(gong)(gong)的景(jing)洪(hong)水電(dian)站(zhan)(zhan)主體工(gong)(gong)程C1標(biao)(biao)(biao)工(gong)(gong)程,于2003年(nian)12月正(zheng)式(shi)開工(gong)(gong),在(zai)開工(gong)(gong)推遲1個(ge)月的情況下(xia),葛(ge)洲(zhou)壩人克服準備工(gong)(gong)程不完(wan)善、原材料供應不足等困(kun)難(nan),僅用半年(nian)時間就提(ti)前實(shi)現了(le)縱(zong)向圍堰混凝土澆(jiao)筑(zhu)(zhu)達到555米(mi)防(fang)汛(xun)高程目標(biao)(biao)(biao),保證(zheng)了(le)縱(zong)向圍堰安全(quan)度(du)(du)汛(xun);隨后在(zai)右岸大壩主體混凝土澆(jiao)筑(zhu)(zhu)中,項目部以比(bi)合同工(gong)(gong)期提(ti)前10個(ge)月的優異成績實(shi)現了(le)右岸大壩分流過水目標(biao)(biao)(biao),保證(zheng)了(le)景(jing)洪(hong)電(dian)站(zhan)(zhan)提(ti)前10個(ge)月截流,創造了(le)景(jing)洪(hong)水電(dian)站(zhan)(zhan)當(dang)年(nian)下(xia)基(ji)坑(keng)、當(dang)年(nian)澆(jiao)筑(zhu)(zhu)、當(dang)年(nian)度(du)(du)汛(xun)、當(dang)年(nian)達到截流設計目標(biao)(biao)(biao)的國(guo)內同類(lei)型電(dian)站(zhan)(zhan)建設的最快速度(du)(du),被專家譽為“景(jing)洪(hong)速度(du)(du)”。
2007年汛后至(zhi)2008年,葛洲(zhou)壩景洪項目(mu)部科(ke)學組織下閘(zha)蓄水項目(mu)施工,最(zui)終實(shi)現(xian)了2月底(di)缺口壩段達到蓄水高程,2008年3月30日,C1標上下游(you)縱向圍堰拆(chai)除全線完工;4月18日,導流底(di)孔5扇封堵閘(zha)門(men)成(cheng)功下閘(zha),提前(qian)7個月實(shi)現(xian)大壩蓄水目(mu)標,為電(dian)站(zhan)首臺(tai)機組2008年6月發(fa)電(dian)奠(dian)定(ding)了堅實(shi)的基礎。
電站蓄水發電后,葛洲壩人認(ren)真(zhen)組織2008年(nian)汛(xun)(xun)后至(zhi)2009年(nian)汛(xun)(xun)前的導流底(di)孔封(feng)堵及下(xia)游引航(hang)道(dao)施(shi)工,在汛(xun)(xun)期(qi)推遲(chi)、下(xia)游引航(hang)道(dao)地質條件變化、工程量增加等不利因(yin)素影響下(xia),精心組織施(shi)工,于4月(yue)(yue)30日提前1個(ge)月(yue)(yue)實現(xian)業主要求的“導墻、邊(bian)坡混凝土澆筑完成”防洪度汛(xun)(xun)目標,并于6月(yue)(yue)中旬完成了枯(ku)期(qi)圍堰拆除,于6月(yue)(yue)30日完成了2號表孔尾坎(kan)澆筑。至(zhi)此(ci),C1標所有(you)項目全(quan)部按合同工期(qi)完成。
據統計(ji),六年來,葛洲壩集團共完成單元工程3135個(ge),合格率(lv)100%,優良率(lv)91%;共創建“樣板(ban)工程”14個(ge)。