文(wen)章來源:中國兵器工(gong)業(ye)集團(tuan)公司 發(fa)布時間:2010-06-11
經過萬余(yu)名(ming)建設者22個月的艱苦(ku)奮戰,中國兵器工(gong)業集團華錦公(gong)司“十(shi)一(yi)五”重點工(gong)程(cheng)建設全面(mian)完成了打樁、基礎和(he)地(di)管(guan)、結構和(he)設備(bei)安裝、工(gong)藝(yi)管(guan)線和(he)電(dian)纜敷設和(he)電(dian)氣設備(bei)安裝5個階段的全部施(shi)工(gong)任務(wu),截止到5月31日(ri),多(duo)個項目陸續(xu)驗收,勝(sheng)利(li)實現(xian)機械竣工(gong)。
儲運工程實現全線機械竣工
5月(yue)31日,該公司“十(shi)一(yi)(yi)五(wu)”重點(dian)工(gong)(gong)(gong)(gong)程(cheng)(cheng)之(zhi)(zhi)一(yi)(yi)的(de)儲(chu)運155公里輸(shu)油管(guan)(guan)線順利通過(guo)竣工(gong)(gong)(gong)(gong)驗收(shou),至此,“十(shi)一(yi)(yi)五(wu)” 工(gong)(gong)(gong)(gong)程(cheng)(cheng)的(de)關(guan)鍵項目(mu)——儲(chu)運工(gong)(gong)(gong)(gong)程(cheng)(cheng)實現(xian)全(quan)線機械(xie)竣工(gong)(gong)(gong)(gong),這也是“十(shi)一(yi)(yi)五(wu)”工(gong)(gong)(gong)(gong)程(cheng)(cheng)第(di)一(yi)(yi)個整體竣工(gong)(gong)(gong)(gong)的(de)項目(mu)。自2008年(nian)3月(yue)1日儲(chu)運工(gong)(gong)(gong)(gong)程(cheng)(cheng)開工(gong)(gong)(gong)(gong)建設(she)(she)以來,按照(zhao)“打造兵器石(shi)化(hua)產業精品工(gong)(gong)(gong)(gong)程(cheng)(cheng)”要求(qiu),堅(jian)持嚴(yan)(yan)(yan)之(zhi)(zhi)又嚴(yan)(yan)(yan)、細(xi)之(zhi)(zhi)又細(xi)、實之(zhi)(zhi)又實的(de)管(guan)(guan)理思(si)路(lu),多方(fang)協調化(hua)解(jie)矛(mao)盾(dun),嚴(yan)(yan)(yan)密推進施(shi)(shi)工(gong)(gong)(gong)(gong)進度(du),嚴(yan)(yan)(yan)肅過(guo)程(cheng)(cheng)質(zhi)量控制,嚴(yan)(yan)(yan)格(ge)保證(zheng)施(shi)(shi)工(gong)(gong)(gong)(gong)安全(quan)。克服(fu)時間緊、任務(wu)重、建設(she)(she)環境復雜(za)、管(guan)(guan)線穿越路(lu)河(he)難(nan)度(du)大等(deng)實際困難(nan),高標準(zhun)、高質(zhi)量完成(cheng)了(le)工(gong)(gong)(gong)(gong)程(cheng)(cheng)建設(she)(she)任務(wu),實現(xian)全(quan)線機械(xie)竣工(gong)(gong)(gong)(gong)。
乙烯工程雙聚裝置順利通過驗收
5月(yue)30日,該公司“十(shi)一五”重點工(gong)(gong)(gong)(gong)(gong)程(cheng)之一的(de)乙(yi)烯工(gong)(gong)(gong)(gong)(gong)程(cheng)聚乙(yi)烯、聚丙烯兩(liang)大主(zhu)體裝置雙(shuang)雙(shuang)通(tong)過總指(zhi)揮(hui)部(bu)驗(yan)收,這是乙(yi)烯工(gong)(gong)(gong)(gong)(gong)程(cheng)率先(xian)通(tong)過驗(yan)收的(de)主(zhu)體裝置。“雙(shuang)聚”項目于2008年2月(yue)14日正(zheng)式(shi)開工(gong)(gong)(gong)(gong)(gong)建設(she)(she),在(zai)15個月(yue)的(de)施(shi)工(gong)(gong)(gong)(gong)(gong)建設(she)(she)中,全(quan)體建設(she)(she)人員(yuan)克服工(gong)(gong)(gong)(gong)(gong)期短、設(she)(she)備到貨晚、雨季施(shi)工(gong)(gong)(gong)(gong)(gong)、設(she)(she)計變(bian)更等多重困難,精心組織,晝夜(ye)施(shi)工(gong)(gong)(gong)(gong)(gong),強力(li)推進(jin)(jin)施(shi)工(gong)(gong)(gong)(gong)(gong)進(jin)(jin)度。在(zai)搶抓施(shi)工(gong)(gong)(gong)(gong)(gong)進(jin)(jin)度的(de)同時,嚴控施(shi)工(gong)(gong)(gong)(gong)(gong)質量,狠抓安全(quan)施(shi)工(gong)(gong)(gong)(gong)(gong),特別是進(jin)(jin)入驗(yan)收階(jie)段,按(an)照“三查(cha)(cha)四定”要求,嚴查(cha)(cha)問(wen)題,深刻整(zheng)改,確保了(le)工(gong)(gong)(gong)(gong)(gong)程(cheng)的(de)順(shun)利竣(jun)工(gong)(gong)(gong)(gong)(gong)驗(yan)收。
乙烯總變電所勝利報捷
5月27日(ri),已投用三(san)個多月的(de)該公司乙(yi)烯總(zong)變(bian)(bian)電(dian)所(suo)順利(li)通(tong)過(guo)(guo)機械竣(jun)工(gong)(gong)驗收。按照工(gong)(gong)程建設(she)“電(dian)氣先行(xing)”的(de)部署和要求,他們先后戰(zhan)勝了設(she)計滯后造成工(gong)(gong)程被迫停工(gong)(gong)、大(da)風(feng)雪影響電(dian)纜敷設(she)等困(kun)難,搶工(gong)(gong)期,抓(zhua)質量(liang),在2009年1月12日(ri)具備(bei)受電(dian)條(tiao)件的(de)基礎(chu)上,于2月25日(ri)實現7臺(tai)變(bian)(bian)壓(ya)器全部具備(bei)向乙(yi)烯各分(fen)變(bian)(bian)電(dian)所(suo)送電(dian)條(tiao)件。隨(sui)著100余項(xiang)問題(ti)的(de)徹底整改,乙(yi)烯總(zong)變(bian)(bian)電(dian)所(suo)全面通(tong)過(guo)(guo)竣(jun)工(gong)(gong)驗收。
油化成品油罐區實現機械竣工
5月(yue)29日,該公司(si)油(you)(you)化成品(pin)油(you)(you)罐區(qu)順利通過竣工(gong)驗收,實(shi)現機(ji)械竣工(gong)。自2008年(nian)3月(yue)28日油(you)(you)化成品(pin)油(you)(you)罐區(qu)破土動工(gong)以來,公司(si)克服時間(jian)緊、任務重(zhong)、設計變更以及(ji)(ji)材料(liao)到貨滯后等(deng)諸多不利因素,科學組織,頑強拼搏,在確保(bao)安全和(he)質量的前(qian)提下,力搶工(gong)期,先后完(wan)成了“5.30”基礎施工(gong)和(he)“9.30”罐體制作以及(ji)(ji)設備及(ji)(ji)工(gong)藝管(guan)線安裝、水壓試(shi)驗、單(dan)機(ji)試(shi)車等(deng)各階段節(jie)點(dian)目標。目前(qian),油(you)(you)化成品(pin)油(you)(you)罐區(qu)已具備試(shi)生產條件。
乙烯水系統全線竣工并投入運行
由(you)該公司(si)乙烯(xi)給(gei)水(shui)及高(gao)壓(ya)消防水(shui)泵站(zhan)、乙烯(xi)雨水(shui)池、污水(shui)泵站(zhan)、第二熱水(shui)站(zhan)、脫鹽水(shui)站(zhan)、給(gei)水(shui)變電所和(he)乙烯(xi)第一(yi)、二循環水(shui)場等8個單(dan)體項(xiang)(xiang)目(mu)組成(cheng)的(de)乙烯(xi)水(shui)系統實現(xian)全線告捷,順利(li)通過竣(jun)工驗收(shou)并已(yi)投入生(sheng)產運行。其中(zhong)(zhong),前6個單(dan)體項(xiang)(xiang)目(mu)被評(ping)為“十一(yi)五(wu)”精品(pin)工程。施工中(zhong)(zhong),他們克服建筑結構復雜、作業面分散、材料到(dao)貨滯(zhi)后、交(jiao)叉作業多等諸多困難(nan),高(gao)標(biao)準、高(gao)質(zhi)量推進工程進度(du)。特(te)別是在收(shou)尾驗收(shou)中(zhong)(zhong),他們嚴格(ge)自檢(jian)自查,查出并徹底整改問題2700余(yu)項(xiang)(xiang),確保(bao)了水(shui)汽(qi)項(xiang)(xiang)目(mu)的(de)高(gao)標(biao)準、高(gao)質(zhi)量竣(jun)工。
公用供熱外管廊實現機械竣工
5月31日,該公(gong)司公(gong)用供(gong)熱(re)外(wai)管廊(lang)順利通過驗收復查,實現(xian)機械(xie)竣工(gong)。該項目(mu)于(yu)2008年(nian)3月11日開工(gong),經過廣大建設者14個月的艱(jian)苦奮戰(zhan),完成管樁施工(gong)632根,澆(jiao)筑混(hun)凝土1100立方米,制作安裝鋼結構1700噸,鋪設各(ge)類管線27條約15000延長米,完成保(bao)溫絕熱(re)工(gong)程3200立方米。特別是攻克了(le)冬季(ji)施工(gong)難題,保(bao)質(zhi)保(bao)量(liang)保(bao)進度完成了(le)1020米φ711高(gao)壓管線施工(gong),確保(bao)了(le)供(gong)熱(re)外(wai)管廊(lang)工(gong)程的高(gao)標準、高(gao)質(zhi)量(liang)、高(gao)效率(lv)竣工(gong)。