葛洲壩集團完成瀘定水電站圍堰防滲施工

文章來源:中國(guo)葛洲壩集團公司  發布時(shi)間:2010-06-11

  由葛洲壩集團基礎公司承擔施工的四川大渡(du)河瀘定水電站2號、3號泄洪(hong)洞出口圍(wei)堰懸掛式混凝土防滲墻工程于5月31日提前(qian)完工。

  四川瀘定水電站位于大渡河瀘定縣城上游2-3公里處,裝機84萬千瓦。工程總投資669642萬元。此次進行施工的2、3號泄洪洞出口圍堰懸掛式混凝土防滲墻工程,施工圍堰軸線長約367米,平均墻深27米,墻厚80厘米,設計工程量為10080平方米,工期要求55天完成。

  葛(ge)洲壩(ba)(ba)集團(tuan)基礎公司于3月(yue)底(di)組織精兵強將及37臺套施(shi)(shi)工(gong)(gong)(gong)設備奔(ben)赴大渡河(he)瀘定(ding)水電(dian)站,投(tou)入該(gai)項目混凝土防滲墻(qiang)施(shi)(shi)工(gong)(gong)(gong)。該(gai)工(gong)(gong)(gong)程(cheng)于4月(yue)12日在220米(mi)軸線上先(xian)期開工(gong)(gong)(gong),5月(yue)12日軸線全面施(shi)(shi)工(gong)(gong)(gong)。因距大渡河(he)較近,受大渡河(he)水位漲落頻繁影響(xiang),對造(zao)孔(kong)槽段(duan)坍塌產生了(le)較大的風(feng)險;為防止造(zao)孔(kong)槽段(duan)坍塌,搶工(gong)(gong)(gong)期、提(ti)高形象進(jin)度,施(shi)(shi)工(gong)(gong)(gong)中(zhong),葛(ge)洲壩(ba)(ba)人克難攻堅,拼搏進(jin)取,精心組織施(shi)(shi)工(gong)(gong)(gong),根據工(gong)(gong)(gong)程(cheng)地質(zhi)實際(ji)情況,在施(shi)(shi)工(gong)(gong)(gong)工(gong)(gong)(gong)藝上采(cai)用了(le)“平打法”、“孔(kong)口回漿(jiang)法”,強化了(le)現場質(zhi)量、安全、文明施(shi)(shi)工(gong)(gong)(gong)管理(li),使施(shi)(shi)工(gong)(gong)(gong)效益(yi)大幅(fu)提(ti)高,推進(jin)了(le)工(gong)(gong)(gong)程(cheng)施(shi)(shi)工(gong)(gong)(gong)的順利進(jin)行。

  經(jing)過(guo)50天(tian)晝夜奮戰(zhan),比計(ji)劃工期提前(qian)了5天(tian)完(wan)工,實現了質(zhi)量、安全零事故(gu)目標,得到華(hua)電業主、中南(nan)監理的高度(du)贊譽。

掃一掃在手機打開當前頁

打印

 

關閉窗口

lutube-lutube下载-lutube下载地址-lutube最新地址 lutube-lutube下载-lutube下载地址-lutube最新地址 lutube-lutube下载-lutube下载地址-lutube最新地址