文章來源:中國(guo)南方電(dian)網有限責(ze)任(ren)公司 發布時間:2010-04-13
截至2009年3月31日,中國南方電網有限責任公司云南電網公司比計劃提前2個月全面完成35千伏及以下線路抗冰加固工程,共完成直供區和農網三級線路加固599條,更換導線891千米,新增、更換水泥電桿9557根,新增鐵塔210基。
針對加(jia)(jia)固工(gong)(gong)(gong)作(zuo)時(shi)間(jian)緊、任務(wu)重、點多面廣的實際情況,云南電(dian)網公司多次召開抗冰加(jia)(jia)固工(gong)(gong)(gong)作(zuo)會議,就融(rong)資、物資供應、工(gong)(gong)(gong)程(cheng)(cheng)管(guan)理(li)、財務(wu)管(guan)理(li)、審計(ji)、監察等工(gong)(gong)(gong)作(zuo)進行周密(mi)部署,確保(bao)加(jia)(jia)固工(gong)(gong)(gong)程(cheng)(cheng)按(an)期完(wan)成。目前,加(jia)(jia)固工(gong)(gong)(gong)程(cheng)(cheng)均已通過(guo)施工(gong)(gong)(gong)單位、縣公司和(he)供電(dian)局(ju)的驗收投運。