文章來源:中國水(shui)利水(shui)電建設集團公(gong)司 發布(bu)時(shi)間(jian):2009-01-03
經過5300余名中蘇員(yuan)工(gong)的艱苦奮戰(zhan)和(he)努力(li)拼搏,蘇丹麥洛(luo)維(wei)大(da)壩工(gong)程各項工(gong)作進(jin)展(zhan)順利,圓滿(man)完(wan)(wan)成(cheng)了(le)(le)2007年工(gong)程計劃和(he)形象(xiang)進(jin)度(du)要求(qiu)。截至(zhi)2007年12月31日,全年累計完(wan)(wan)成(cheng):土(tu)(tu)石(shi)方開挖49萬立(li)方米(mi),土(tu)(tu)石(shi)方填筑(zhu)466萬立(li)方米(mi),混凝土(tu)(tu)澆筑(zhu)49萬立(li)方米(mi),基礎處(chu)理約2.6萬米(mi)。預計完(wan)(wan)成(cheng)工(gong)程產(chan)(chan)值(zhi)17億人(ren)(ren)民幣,取得了(le)(le)月平均創產(chan)(chan)值(zhi)1.42億人(ren)(ren)民幣的驕(jiao)人(ren)(ren)業(ye)績(ji),創造(zao)了(le)(le)開工(gong)以來麥洛(luo)維(wei)大(da)壩工(gong)程完(wan)(wan)成(cheng)產(chan)(chan)值(zhi)最高(gao)的一(yi)年。
2007年(nian)是麥(mai)(mai)洛維大(da)(da)壩工(gong)(gong)(gong)(gong)程(cheng)施(shi)(shi)工(gong)(gong)(gong)(gong)的(de)關鍵年(nian)。為適應麥(mai)(mai)洛維大(da)(da)壩工(gong)(gong)(gong)(gong)程(cheng)進展帶(dai)來的(de)新(xin)(xin)變化(hua)、新(xin)(xin)特點和新(xin)(xin)要求,在(zai)中國水電集(ji)團、CCMDJV和七(qi)五聯營體兩級董事會的(de)大(da)(da)力(li)支持下,蘇丹麥(mai)(mai)洛維項目(mu)部根據工(gong)(gong)(gong)(gong)程(cheng)需要,及(ji)時(shi)增(zeng)(zeng)加人力(li)、設備資源,其中:增(zeng)(zeng)加中方人員481人,增(zeng)(zeng)加當地(di)雇員375人,新(xin)(xin)增(zeng)(zeng)總值(zhi)達258.2萬美元施(shi)(shi)工(gong)(gong)(gong)(gong)設備50臺,并采(cai)取加強(qiang)內部管理、改進施(shi)(shi)工(gong)(gong)(gong)(gong)工(gong)(gong)(gong)(gong)藝(yi)等措(cuo)施(shi)(shi),有(you)效地(di)解決了(le)人力(li)、設備資源不(bu)足(zu),極大(da)(da)地(di)提(ti)(ti)高了(le)施(shi)(shi)工(gong)(gong)(gong)(gong)進度(du)。并出臺一系列(lie)現(xian)場施(shi)(shi)工(gong)(gong)(gong)(gong)管理及(ji)獎勵文件,強(qiang)化(hua)設備使用率,提(ti)(ti)高施(shi)(shi)工(gong)(gong)(gong)(gong)生產率,為麥(mai)(mai)洛維大(da)(da)壩工(gong)(gong)(gong)(gong)程(cheng)全線(xian)搶(qiang)工(gong)(gong)(gong)(gong)提(ti)(ti)供了(le)有(you)力(li)的(de)保障。
面對蘇丹(dan)麥洛維(wei)(wei)大壩工(gong)(gong)程施工(gong)(gong)高峰期,在工(gong)(gong)期緊(jin)、施工(gong)(gong)強度大、物資匱乏、氣候(hou)炎熱(re)等(deng)諸多(duo)壓力(li)和重(zhong)重(zhong)困難下,麥洛維(wei)(wei)項目部緊(jin)緊(jin)圍繞“三期導流”目標,全體(ti)員(yuan)工(gong)(gong)齊心協力(li),按照既(ji)定目標,連續(xu)作戰,晝夜(ye)施工(gong)(gong),將(jiang)麥洛維(wei)(wei)大壩工(gong)(gong)程施工(gong)(gong)推(tui)向高潮。混(hun)凝土澆(jiao)筑(zhu)、土石(shi)方(fang)開挖填筑(zhu)的(de)日(ri)產(chan)量、周產(chan)量、月(yue)產(chan)量一路(lu)攀(pan)升,11月(yue)土石(shi)方(fang)填筑(zhu)創(chuang)52萬立(li)方(fang)米高產(chan)記錄,12月(yue)混(hun)凝土澆(jiao)筑(zhu)創(chuang)造5.6萬立(li)方(fang)米高產(chan)紀錄,使所(suo)有施工(gong)(gong)部位全線(xian)告捷。
“百(bai)年大計,質量第一(yi),拼搶工(gong)(gong)(gong)期,方案先行(xing)”。麥(mai)洛維項(xiang)目部完善質量管理(li)體系(xi)及(ji)各種質量管理(li)制度(du),加(jia)強(qiang)(qiang)工(gong)(gong)(gong)程質量管理(li),加(jia)強(qiang)(qiang)與(yu)監理(li)工(gong)(gong)(gong)程師溝通與(yu)交流(liu)(liu),并對現場施(shi)(shi)(shi)工(gong)(gong)(gong)全過程進行(xing)技術指導(dao)、生(sheng)產監督。2007年度(du)共完成3686個單(dan)元(yuan)工(gong)(gong)(gong)程驗收,驗收合(he)格(ge)率為100%,一(yi)次驗收合(he)格(ge)率為96.4%。全力(li)保障麥(mai)洛維項(xiang)大壩工(gong)(gong)(gong)程技術供應,2007年共完成25個施(shi)(shi)(shi)工(gong)(gong)(gong)工(gong)(gong)(gong)藝、方案的編寫工(gong)(gong)(gong)作,并及(ji)時(shi)更新12個施(shi)(shi)(shi)工(gong)(gong)(gong)方案。其中,三(san)期導(dao)流(liu)(liu)方案的優化,采(cai)取(qu)(qu)溢(yi)流(liu)(liu)壩所(suo)有堰(yan)孔混(hun)凝土(tu)連續澆筑(zhu)方案,大大減少了臨時(shi)過流(liu)(liu)混(hun)凝土(tu)施(shi)(shi)(shi)工(gong)(gong)(gong)縫(feng)面及(ji)鋼筋(jin)處理(li),為三(san)期導(dao)流(liu)(liu)施(shi)(shi)(shi)工(gong)(gong)(gong)爭(zheng)取(qu)(qu)了寶貴的時(shi)間。
自2007年10月初三(san)期導(dao)流施工(gong)正式啟動以(yi)來(lai)(lai),七(qi)五聯營體董蘇丹麥洛(luo)維項目(mu)部科(ke)學組(zu)織,合(he)理(li)安排施工(gong)資源,掀起了三(san)期導(dao)流和確保(bao)一、二機組(zu)發電(dian)的施工(gong)高(gao)潮(chao),進而向全面完成年度各項任(ren)務目(mu)標(biao)沖刺。目(mu)前(qian),麥洛(luo)維大壩工(gong)程2A、2B、2C、3D標(biao)各個部位的形(xing)象(xiang)面貌達到預期目(mu)標(biao),三(san)期導(dao)流工(gong)程施工(gong)進展順利。截(jie)至2007年底,開(kai)工(gong)以(yi)來(lai)(lai)累(lei)計(ji)完成:土(tu)石(shi)方(fang)開(kai)挖849.2萬(wan)(wan)立(li)方(fang)米(mi),占(zhan)合(he)同量(liang)100%;土(tu)石(shi)方(fang)回填1218.92萬(wan)(wan)立(li)方(fang)米(mi),占(zhan)合(he)同量(liang)85%;混凝土(tu)澆(jiao)筑161.56萬(wan)(wan)立(li)方(fang)米(mi),占(zhan)合(he)同量(liang)90%;鋼筋制安9.4萬(wan)(wan)噸,占(zhan)合(he)同量(liang)85%,基礎處理(li)24.27萬(wan)(wan)米(mi),占(zhan)合(he)同量(liang)100%。
2008年,麥洛維大壩工程建設任務仍十分繁重,計劃完成7億人民幣產值。中國水電集團七五聯營體蘇丹麥洛維項目部將再接再厲,嚴格按合同履約,實現開源節流,提高經濟效益,確保三期導流和1、2號機組發電里程碑目標順利實現,為奪取麥洛維大壩工程最后的勝利,為打造中國水電國際品牌而努力奮斗。