文章(zhang)來源:中國葛洲(zhou)壩集團公司(si) 發布(bu)時間:2008-12-25
12月10日,葛洲壩一公司承建的南水(shui)北調中線干線京石段應急供(gong)水(shui)工程直管或代(dai)建四標主體工程全面完工。
南水北調中線干線京石段應急供水工程直管或代建第四標總長6.74公里,標段內有石渠與土渠兩種類型及四種坡比的襯砌施工,施工技術復雜,難度大,工期壓力大。
為圓滿完成施(shi)工(gong)(gong)(gong)(gong)任務,葛洲壩一公司(si)南水北調項目部召開(kai)動員會,加大人力(li)(li)、物(wu)力(li)(li)投(tou)入,加強現(xian)場施(shi)工(gong)(gong)(gong)(gong)管理(li),嚴格施(shi)工(gong)(gong)(gong)(gong)質量控(kong)制(zhi),實行(xing)獎懲制(zhi)度,極大地調動了員工(gong)(gong)(gong)(gong)的生產積極性(xing)。施(shi)工(gong)(gong)(gong)(gong)現(xian)場氣氛熱烈,工(gong)(gong)(gong)(gong)程(cheng)形象(xiang)日新月異(yi)。
據了解,截至目前,項目部已累計完成石渠襯砌3465米,土渠襯砌4620米,分別占總任務的90%和52%,工程進度處于直管四個標段的前列。