文章來源:中國石油化工集團公司 發布(bu)時間:2008-11-16
11月(yue)9日上午,舟(zhou)山國家(jia)石(shi)油(you)儲(chu)備項目(II標段)二期(qi)工(gong)程(cheng)中(zhong)交驗(yan)收(shou)(shou)會(hui),在舟(zhou)山國家(jia)石(shi)油(you)儲(chu)備基地有限責任公(gong)司(si)召開。十建(jian)公(gong)司(si)舟(zhou)山國家(jia)石(shi)油(you)儲(chu)備項目部(bu)總工(gong)程(cheng)師張德林對(dui)(dui)工(gong)程(cheng)施工(gong)管理情(qing)況(kuang)進(jin)行(xing)了匯報,業(ye)主及與會(hui)專(zhuan)家(jia)對(dui)(dui)中(zhong)交工(gong)程(cheng)進(jin)行(xing)了驗(yan)收(shou)(shou)確認,對(dui)(dui)工(gong)程(cheng)技(ji)術資料進(jin)行(xing)了驗(yan)收(shou)(shou)檢查。
舟山(shan)國家石(shi)油儲(chu)備項(xiang)目(II標段)二期(qi)工(gong)(gong)(gong)程(cheng)由(you)6臺10萬立方米儲(chu)罐(guan)主(zhu)體及罐(guan)體泡沫、噴淋系統安(an)裝,工(gong)(gong)(gong)藝(yi)管線安(an)裝工(gong)(gong)(gong)程(cheng),土(tu)建工(gong)(gong)(gong)程(cheng)、電氣安(an)裝工(gong)(gong)(gong)程(cheng),監(jian)視(shi)塔及陰極保護(hu)等12個單(dan)位工(gong)(gong)(gong)程(cheng)組成(cheng)。
合(he)同(tong)規定,施工有效工期(qi)390天。經過十(shi)建(jian)(jian)公司項(xiang)目部(bu)合(he)理組織(zhi)施工,實際(ji)施工天數為353天,比計(ji)劃工期(qi)縮短了(le)37天。截至9月27日,十(shi)建(jian)(jian)公司舟(zhou)山國家石油儲備項(xiang)目部(bu)完成了(le)合(he)同(tong)規定的儲罐(guan)安(an)裝、工藝管線安(an)裝、防腐、土建(jian)(jian)、電氣(qi)等全部(bu)施工任務,達(da)到(dao)了(le)合(he)同(tong)實物工程量的中(zhong)交驗收條件(jian)。
在驗收(shou)總結會上,舟山國儲基地有限責(ze)任(ren)公(gong)(gong)司(si)副總經理朱根(gen)民(min)對(dui)十建公(gong)(gong)司(si)承擔(dan)的(de)II標段(duan)二期(qi)工(gong)程給予了(le)高(gao)度評(ping)價,稱贊十建公(gong)(gong)司(si)“在抓質量進度的(de)同時,不忘文明施工(gong)和安全管(guan)理,工(gong)程自(zi)開工(gong)以來(lai),未發生(sheng)一起重大安全、質量事(shi)故,工(gong)程施工(gong)質量達到了(le)優(you)良(liang)標準”。
十建公司舟山國儲庫項目部經理翁大龍、施工經理孫建軍、控制經理張光,舟山國家石油儲備基地有限責任公司有關方面負責人、南京長江監理公司、中石油管道局設計院,舟山市質檢站、中石油東方無損檢測公司、中石油質檢站等各參建單位及相關部門人員參加了交工儀式。