文章來源:中國華(hua)電集司團公司 發布時間:2008-09-18
2007年9月9日上(shang)(shang)午(wu)11時16分,隨(sui)著巨型(xing)風(feng)機(ji)槳葉被吊(diao)裝(zhuang)到68米高空的塔架(jia)上(shang)(shang),由(you)華(hua)電(dian)(dian)工程公司和上(shang)(shang)海(hai)電(dian)(dian)氣聯合總承包的山西右玉(yu)41.25MW風(feng)電(dian)(dian)場項目的首臺機(ji)組安(an)裝(zhuang)成(cheng)功(gong),標志著山西省實現了風(feng)力發電(dian)(dian)零(ling)的突破。
該項(xiang)目(mu)由(you)山西(xi)國際(ji)電(dian)力(li)集團公司(si)投(tou)資,由(you)華(hua)電(dian)工(gong)(gong)(gong)程(cheng)公司(si)負責(ze)工(gong)(gong)(gong)程(cheng)承包(bao)管理,上(shang)海(hai)(hai)電(dian)氣風電(dian)設(she)備有限(xian)公司(si)(華(hua)電(dian)工(gong)(gong)(gong)程(cheng)和上(shang)海(hai)(hai)電(dian)氣股份公司(si)的合資公司(si))負責(ze)SEC-1250KW變槳變速風電(dian)機(ji)組的供(gong)貨,華(hua)電(dian)重(zhong)工(gong)(gong)(gong)機(ji)械公司(si)負責(ze)主(zhu)機(ji)68M塔架供(gong)貨。該項(xiang)目(mu)為中(zhong)國第一個風電(dian)EPC項(xiang)目(mu),于(yu)2007年4月28日開工(gong)(gong)(gong)建設(she),全(quan)部(bu)工(gong)(gong)(gong)程(cheng)將于(yu)08年底(di)完工(gong)(gong)(gong)。同時進行的山西(xi)平魯33.75MW項(xiang)目(mu),將于(yu)07年10月底(di)開始(shi)安裝。