文章來源(yuan):中國能源(yuan)建設(she)集團有限公(gong)司 發布時間:2014-08-06
當地時間7月31日,中國能源建設集團有限公司承建的委內瑞拉比西亞電站1號燃機并網一次成功。
1號機組并網后系統各項參數穩定,保護裝置投入正常,整個系統運轉穩定,各項指標優良。自進入試運階段以來,中國能建天津電建及時盤點試運計劃,組織大量的人力進行消缺處理。1號燃機啟動并網期間,中國能建天津電建項目部全體人員與業主方、甲方生產技術人員、運行人員、設備維護人員和調試單位、設備廠家等通力合作,及時消除各類缺陷。
委內瑞拉(la)比西(xi)亞(ya)項目(mu)是中國能建(jian)(jian)天津(jin)電(dian)(dian)(dian)(dian)(dian)(dian)建(jian)(jian)在南美市(shi)場承建(jian)(jian)的首(shou)個項目(mu)。該項目(mu)位于(yu)委內瑞拉(la)西(xi)部梅里達州MERIDA比西(xi)亞(ya)市(shi),建(jian)(jian)設一座(zuo)總(zong)裝機(ji)容量50萬(wan)千瓦級(ji)的火電(dian)(dian)(dian)(dian)(dian)(dian)站以及(ji)配套(tao)輸變電(dian)(dian)(dian)(dian)(dian)(dian)工(gong)程,分兩期(qi)建(jian)(jian)設。一期(qi)為2臺單循環燃氣輪發電(dian)(dian)(dian)(dian)(dian)(dian)機(ji)組,一期(qi)發電(dian)(dian)(dian)(dian)(dian)(dian)量40萬(wan)千瓦級(ji),二期(qi)增加余熱鍋爐和汽輪機(ji),總(zong)發電(dian)(dian)(dian)(dian)(dian)(dian)量57萬(wan)千瓦。