文章(zhang)來源:中(zhong)國有(you)色(se)礦業(ye)集團有(you)限公司 發(fa)布時(shi)間:2014-05-23
近日,中國有色集團出資企業十五冶利比里亞項目部相繼實現了取水浮船經二級加壓泵站到高位水池生產給水系統一次輸水成功、粗碎站到粗礦堆給料系統試車成功,這兩個重要節點得成功均得益于項目部電器調試班的技術攻關。
4月初,業主單(dan)位還(huan)在為了沒有(you)試(shi)車(che)(che)電(dian)(dian)(dian)(dian)源而擔(dan)心,由于(yu)條件(jian)所限,只(zhi)能(neng)采取(qu)臨電(dian)(dian)(dian)(dian)方(fang)式進行(xing)試(shi)車(che)(che),借用碼頭項(xiang)目的發(fa)電(dian)(dian)(dian)(dian)機(ji)組發(fa)電(dian)(dian)(dian)(dian)。由于(yu)試(shi)車(che)(che)時(shi)間迫在眉睫(jie),調試(shi)班集(ji)思廣益,根據(ju)現(xian)(xian)場(chang)的實(shi)際情況和廠(chang)家(jia)的設備特點(dian),提出(chu)了“采用廠(chang)家(jia)發(fa)電(dian)(dian)(dian)(dian)機(ji)本體加現(xian)(xian)場(chang)配電(dian)(dian)(dian)(dian)設施,現(xian)(xian)場(chang)利用項(xiang)目部已有(you)的庫存發(fa)電(dian)(dian)(dian)(dian)機(ji)控(kong)制板(ban)制作(zuo)控(kong)制箱完善控(kong)制線路”的方(fang)案。此次方(fang)案經現(xian)(xian)場(chang)多次試(shi)驗(yan)成功,實(shi)現(xian)(xian)了最低(di)配置最大效能(neng),在3天時(shi)間內就(jiu)可獨立提供(gong)(gong)試(shi)運行(xing)的臨電(dian)(dian)(dian)(dian)供(gong)(gong)給,從而為試(shi)車(che)(che)贏得了寶貴的時(shi)間。