文章來(lai)源:中(zhong)國能源建設集團有限公(gong)司 發(fa)布時間:2016-11-18
11月16日,中(zhong)國能(neng)建安徽電建二公司承(cheng)建的三峽新能(neng)源山西大同左(zuo)云100MWp光伏發(fa)電項(xiang)目開工建設。
工(gong)(gong)程(cheng)位于山(shan)西(xi)省大同市(shi)左云(yun)縣,該(gai)地區(qu)日照時(shi)間長、輻射強度高、早晚溫差大,太陽(yang)能資源豐(feng)富,適宜建(jian)(jian)設(she)大型(xing)光伏電(dian)站。電(dian)站建(jian)(jian)成(cheng)后將緩解西(xi)部(bu)山(shan)區(qu)電(dian)力激增(zeng)的需求,提高周(zhou)邊電(dian)網的供電(dian)能力及可靠性(xing),為山(shan)區(qu)人民送去光明。該(gai)項目是安徽(hui)電(dian)建(jian)(jian)二公司簽訂(ding)的單體(ti)規模(mo)最大的光伏電(dian)站PC工(gong)(gong)程(cheng),主要(yao)承(cheng)建(jian)(jian)裝(zhuang)機容量為105MW光伏場(chang)區(qu)及35kV線路工(gong)(gong)程(cheng),分兩個標段施工(gong)(gong),總(zong)投資9.5億元,計劃(hua)2016年6月全部(bu)建(jian)(jian)成(cheng)投產。
前期(qi),由于項目(mu)是山地光伏,位于大同(tong)市采煤沉(chen)陷區內(nei),現場無(wu)進山道路(lu),安徽(hui)電(dian)建二公司大同(tong)項目(mu)部提前策劃(hua),與(yu)業主、附(fu)近村委會(hui)溝通(tong)協商解決道路(lu)問題。施(shi)工(gong)(gong)人員在大雪紛(fen)飛(fei)中劈山開路(lu),遇溝填石,經(jing)過兩周的精(jing)心施(shi)工(gong)(gong),各施(shi)工(gong)(gong)區域的進場道路(lu)已全部修建完成,為(wei)下(xia)一步工(gong)(gong)程順利(li)推(tui)進奠定了基礎。