截至4月14日12時,中俄東線中段控(kong)制性工程遼河盾構穿越已經掘(jue)進1556米,距貫通僅剩(sheng)264米。
2020年(nian),中(zhong)(zhong)國石油(you)旗(qi)下中(zhong)(zhong)油(you)管(guan)道負責建設(she)油(you)氣基(ji)礎設(she)施重點(dian)工(gong)(gong)程(cheng)有7項,其(qi)中(zhong)(zhong)5項納入國家(jia)2020年(nian)油(you)氣基(ji)礎設(she)施重點(dian)工(gong)(gong)程(cheng),包括中(zhong)(zhong)俄東(dong)(dong)線(xian)中(zhong)(zhong)段(長(chang)(chang)嶺—永清(qing))、福州聯(lian)絡線(xian)、中(zhong)(zhong)俄東(dong)(dong)線(xian)南段(永清(qing)—上海)、長(chang)(chang)沙(sha)聯(lian)通(tong)工(gong)(gong)程(cheng)、中(zhong)(zhong)國海油(you)蒙西管(guan)道與中(zhong)(zhong)國石油(you)陜(shan)京二三線(xian)聯(lian)通(tong)工(gong)(gong)程(cheng)、中(zhong)(zhong)俄東(dong)(dong)線(xian)永清(qing)聯(lian)通(tong)配套工(gong)(gong)程(cheng)。
為(wei)高質量(liang)建(jian)(jian)設好重點(dian)管(guan)道工程(cheng)(cheng),中(zhong)油管(guan)道公司(si)及地區管(guan)道企(qi)業(ye)認真(zhen)抓(zhua)好工程(cheng)(cheng)安(an)全(quan)質量(liang)管(guan)理工作,每(mei)日落實(shi)作業(ye)前安(an)全(quan)分析、疫(yi)情防(fang)(fang)控措施(shi)和現(xian)場安(an)全(quan)風險防(fang)(fang)控日檢(jian)查制度(du),持續加強風險識(shi)別與管(guan)控,確保管(guan)道工程(cheng)(cheng)建(jian)(jian)設項(xiang)目安(an)全(quan)有序推進。從3月10日起(qi),中(zhong)油管(guan)道公司(si)組織在建(jian)(jian)重點(dian)項(xiang)目每(mei)日開(kai)展各項(xiang)防(fang)(fang)疫(yi)和安(an)全(quan)風險檢(jian)查,累計檢(jian)查3.6759萬(wan)項(xiang),發現(xian)問題16項(xiang),已(yi)全(quan)部(bu)整改完(wan)畢(bi);3月中(zhong)下旬(xun),組織6名焊接、無損檢(jian)測專(zhuan)家開(kai)展中(zhong)俄東線北(bei)段、福州聯絡線等管(guan)道隱(yin)患(huan)治理工程(cheng)(cheng)焊接及檢(jian)測工藝方案專(zhuan)項(xiang)檢(jian)查;同時,結(jie)合(he)我國北(bei)方及南方地區逐(zhu)步進入汛期的實(shi)際(ji),提(ti)前完(wan)善(shan)預報預警(jing),加強應急(ji)管(guan)理,提(ti)升處(chu)置能力,防(fang)(fang)控汛期風險。
從當(dang)前重點工(gong)程(cheng)(cheng)(cheng)(cheng)施工(gong)進展來看,中(zhong)俄東(dong)線(xian)中(zhong)段(duan)線(xian)路(lu)工(gong)程(cheng)(cheng)(cheng)(cheng)累計到(dao)場17個標(biao)段(duan)146個機組,到(dao)場率91.8%;福州(zhou)聯絡線(xian)工(gong)程(cheng)(cheng)(cheng)(cheng)管(guan)道(dao)線(xian)路(lu)完成15.3公里,占管(guan)線(xian)全長的84%;中(zhong)俄東(dong)線(xian)南段(duan)已經通過國家應急管(guan)理(li)部安(an)評批復,控制性工(gong)程(cheng)(cheng)(cheng)(cheng)長江(jiang)盾(dun)構(gou)隧道(dao)今年1月防(fang)洪(hong)評價(jia)已通過審查;長沙聯通工(gong)程(cheng)(cheng)(cheng)(cheng)以及(ji)中(zhong)國海油蒙西管(guan)道(dao)與陜京二三線(xian)聯通工(gong)程(cheng)(cheng)(cheng)(cheng)、中(zhong)俄東(dong)線(xian)聯通配(pei)套工(gong)程(cheng)(cheng)(cheng)(cheng)也都進展順利,按計劃均在年內建成。
【責任編輯(ji):趙(zhao)藝涵(han)】