文章來源(yuan):中國石油天然(ran)氣集團(tuan)有限(xian)公(gong)司 發(fa)布時(shi)間:2020-03-21
3月(yue)15日,中俄東線天然氣管(guan)道(dao)工(gong)程嫩江主(zhu)河道(dao)盾構工(gong)程隧(sui)道(dao)洞(dong)門封堵完成,意(yi)味著隧(sui)道(dao)正式貫通,比計劃(hua)工(gong)期提前近一個月(yue)。
中俄東線天(tian)然氣管(guan)道工(gong)(gong)程(cheng)是中俄兩(liang)國(guo)全(quan)面加強能源合作、深化(hua)全(quan)面戰(zhan)略(lve)協作伙伴關系的跨國(guo)工(gong)(gong)程(cheng),是服務國(guo)家“一帶一路”倡(chang)議、振興東北老工(gong)(gong)業基(ji)(ji)地、帶動基(ji)(ji)礎工(gong)(gong)業發展、構建(jian)我國(guo)四大能源通道的戰(zhan)略(lve)性工(gong)(gong)程(cheng)。
嫩江(jiang)盾構工(gong)程(cheng)作為(wei)(wei)中俄東線北段的一項(xiang)重(zhong)要控制(zhi)性工(gong)程(cheng),始(shi)發井(jing)位于(yu)黑(hei)龍(long)江(jiang)省大慶市肇源(yuan)縣茂興鎮自力(li)村(cun),接收井(jing)位于(yu)吉林(lin)省松原市前郭(guo)縣嫩江(jiang)村(cun),盾構隧道長1224.7米(mi),內徑3.08米(mi),穿(chuan)越地層主要為(wei)(wei)粉(fen)質(zhi)黏(nian)土(tu)、粉(fen)砂、黏(nian)土(tu)等(deng)復雜結構。施(shi)工(gong)期(qi)間,項(xiang)目部與施(shi)工(gong)、監理(li)單位就工(gong)期(qi)和存(cun)在(zai)的風(feng)險(xian)進行深入研討,決(jue)定采取(qu)水(shui)(shui)下破洞法貫(guan)通,有效規避粉(fen)砂及粉(fen)質(zhi)黏(nian)土(tu)層破洞帶來的涌水(shui)(shui)涌砂、地面(mian)沉降等(deng)風(feng)險(xian),同時兩(liang)次優化、縮(suo)短施(shi)工(gong)工(gong)期(qi),確保工(gong)程(cheng)安全高效貫(guan)通。
管(guan)道局(ju)等(deng)(deng)施工(gong)單位合(he)理調配資源,通過改造設(she)備(bei)、更換(huan)專用刀具、調整掘(jue)進(jin)(jin)(jin)參(can)數(shu)等(deng)(deng)一系(xi)列措施,在嚴寒(han)中攻(gong)克(ke)了600多(duo)米(mi)長的黏土地(di)層(ceng)掘(jue)進(jin)(jin)(jin)、多(duo)次進(jin)(jin)(jin)艙清淤等(deng)(deng)難(nan)題。同時,施工(gong)單位加快(kuai)推進(jin)(jin)(jin)實施智慧管(guan)道建設(she),在施工(gong)現場設(she)立遠程(cheng)監控系(xi)統,對(dui)盾(dun)構隧道掘(jue)進(jin)(jin)(jin)參(can)數(shu)進(jin)(jin)(jin)行實時傳輸,24小(xiao)時全(quan)(quan)程(cheng)監控盾(dun)構機掘(jue)進(jin)(jin)(jin)姿態,確保工(gong)程(cheng)安(an)全(quan)(quan)和質量全(quan)(quan)面受控。
【責任編輯:姚騰】